How to Add Dates to Units and Lessons in a Long-Range Plan

To add dates to Units & Lessons in a Long-Range Plan, follow the below steps:

  1. Open an existing Long-Range Plan by following the steps in this document

  2. To add a date on a Unit, Click on the Add Dates button

  3. The calendar is displayed to select the Dates

  4. Select a Date in the Calendar, the selected date is displayed on the Unit.

  5. To add a date on a Unit, Click on the Add Dates button.

  6. Upon clicking the Add Dates button, Today's date is selected by default.

  7. To change the date, click on the calendar icon.

  8. The calendar is displayed, select a date from the calendar.

    The date gets updated:

  9. Follow the above steps to update the dates for all the Lessons and Units.

  10. Click on the Calendar tab to view the Lessons and Units in the monthly or weekly calendar: